Construction Management

Construction ManagementConstruction Management reviews and provides design recommendation to Capital Projects prior to advertisement of a bid, takes responsibility for management of the construction process from bid opening through project completion, evaluates any claims submitted by Contractors, performs all field quality control, prepares inspection reports, and handles all warranty work notification and verification.  Construction Management also provides these same services to other Sonoma County agencies, assisting County Departments that don’t regularly contract projects.  Towards the end of this page is the lists of projects in-progress or projects that have been completed in the past two years.

 

Project Management Services

Construction Management and Technical Writing sections also perform document preparation and project management for other government agencies.  Some of the services that have been performed on behalf of other government agencies are: contract document preparation; advertising and bidding projects; administering construction contract; and providing claims and dispute resolution support.  If you are a government agency and wish to obtain more information about project management services the Agency can perform for your organization, please click here to submit an information request form.

Listed below are some of the agencies that have utilized Construction Management’s project management services:

 

Agency: Sonoma County Agricultural Preservation and Open Space District
Project Name:
Improvements for Plum Ranch Road and Cleland Ranch Road (Saddle Mountain Property)

Agency: Sonoma County Fairgrounds:
Project Name:
(proposal submitted) RFI#2009-2011 Contract Management Services for Caltrans Stormwater Mitigation Improvements (Brookwood Avenue Parking Lot)

 

 

Projects In-Progress

Project Title:  Sonoma Valley County Sanitation District (SVCSD) Treatment Plant Aboveground Diesel Fuel Tank
Date Started:
July 27, 2009
Description:
    The Work consists of providing an 8,000-gallon aboveground diesel fuel tank at SVCSDs treatment plant at 22675 8th Street East, Sonoma, California, outside the limits of the City of Sonoma.  The Work includes, but is not limited to, 500 gallons of diesel fuel, transferring of diesel fuel from SVCSDs existing underground fuel tank, related grading, concrete foundation, underground utility work, piping, valves, controls, safety devices, and miscellaneous electrical work.

 

Project Title:  Mirabel Generator Replacement
Date Started:
October 13, 2008
Description:
    The work consists of replacement of two generators, switchgear and transformer with two 2,500-kilowatt, 12,470 volt Agency-furnished containerized generators and day tanks.  Work also consists of providing switchgear, protective relays, transformer, and appurtenenances and site-improvements at Agency's Mirabel Facility.

 

Project Title:  Matanzas Creek Reservoir Sediment Removal Project Revegetation
Date Started:
January 14, 2008
Description:
    The work consists of implementation of on-Site revegetation involving oak woodlands, wetlands, and riparian area of Agency's Matanzas Creek Reservoir Sediment Removal Project, at Matanzas Creek Reservoir off Bennett Valley Road, near Grange Road, Sonoma County, California, including but not limited to: preparation and submittal of Technical Plan; collection and installation of sprigs; installation of Agency-furnished container-grown plants; submittal of monitoring reports; and maintenance for three years after installation is complete.  Maintenance activities include watering and weeding; plant monitoring, submitting monthly reports, survival assessment, providing replacement plants as necessary, and all other post-installation work described in the Agency-approved Technical Plan.

 

Projects Completed

Project Title:  Administrative Facilities at 404 Aviation Blvd - Tenant Improvements: Glazing, Fire Suppression and Ceiling Repair Project
Date Started:
November 6, 2008                  
Date Completed:
   February 13, 2009
Description:
    The work consisted of installation of glazing and glass, fire suppression systems, and repair work on ceilings and relocation of existing HVAC registers as needed to accommodate new construction in the new offices and conference rooms.

 

Project Title:  Administrative Facilities at 404 Aviation Blvd - Tenant Improvements: Partition Walls, Doors, Frames, Hardware Project
Date Started:
November 5, 2008
Date Completed:
   January 5, 2009
Description:
    Work consisted of construction of offices and conference rooms at Owner's office at 404 Aviation Blvd, Santa Rosa, CA, including without limitation, furnishing and installation of partition walls, doors, frames, and hardware for the new offices and conference rooms.

 

Project Title:  Administrative Facilities at 404 Aviation Blvd - Tenant Improvements: Electrical Work
Date Started:
November 5, 2008
Date Completed:
   January 5, 2009
Description:
    Work consisted of labor to install electrical receptacles and wiring, telephone and data receptacles and wiring, and relocation of ceiling mounted light fixtures and ceiling mounted electrical appurtenances at the new offices and conference rooms.

 

Project Title:  Administrative Facilities at 404 Aviation Blvd Tenant Improvements - Parking Lot Modification Project
Date Started:
February 4, 2009
Date Completed:
  February 12, 2009
Description:
    The work consisted of providing ceramic traffic buttons, signs, truncated domes, slope correction, concrete ramp, blackout, striping and wheel stops.

 

Project Title:  Administrative Facilities at 404 Aviation Blvd - T8 to T8 Lighting Retrofit
Date Started:
August 16, 2008
Date Completed:
  October 15, 2008
Description:
    Work consisted of removing, disposing of, and replacing ballasts, light fixtures, and appurtenances at 404 Aviation Blvd, Santa Rosa, CA.

 

Project Title:  Airport-Larkfield-Wikiup Sanitation Zone Treatment Plant Photovoltaic Project
Date Started:
April 9, 2009
Date Completed:
  April 10, 2009
Description:
    Work consisted of providing, furnishing, and installing 37 photovoltaic panels, wiring, and reinstallation of 18 existing modules including recommissioning, support services, construction, clean-up, and all other construction services, of any type, providing and furnishing all necessary supplies, materials, and equipment, and all necessary supervision, labor, services required to reconstruct, and recommission an operational and fully functional integrated Photovoltaic System.

 

Project Title:  Occidental County Sanitation District Collection System Replacement Project
Date Started:
August 6, 2007
Date Completed:
   August 23, 2008
Description:
    Work consisted of removal or abandonment of portions of the existing gravity sewer system and providing approximately 3,550 feet of gravity sewer main and the associated manholes, laterals, and cleanouts.  The existing sewer main generally consisted of 6-inch slip-lined asbestos cement pipe.  The new gravity sewer system consists primarily of 8-inch PVC, High Density Polyethylene (HDPE), and Ductile Iron (DI) Pipe; 48-inch and 60-inch PVC, HDPE, or DI laterals.  Laterals generally terminate with a new cleanout near the property lines.

 

Project Title:  South Park County Sanitation District Moorland Avenue Collection System Replacement Project
Date Started:
May 1, 2008
Date Completed:
   December 12, 2008
Description:
    Work consisted of removal and siposal of approximately 105 feet of existing 8-inch diameter sewer main pipe, abandonment of approximately 2,299 feet of existing 6-inch and 8-inch diameter sewer main pipe, construction of approximately 2,404 feet of new 8-inch diameter sewer main pipe paralleling the existing sewer main, construction of new appurtenant manholes and in-place abandonment of existing manholes, removal and replacement of appurtenant 4-inch diameter sewer laterals, and abandonment of appurtenance 4-inch diameter sewer laterals where indicated on the drawings.

 

Project Title:  Sonoma Valley County Sanitation District Sonoma Developmental Center Water Efficiency Project
Date Started:
November 10, 2008
Date Completed:
   June 11, 2009
Description:
    Work consisted of providing floor-mounted toilets, flushometer valve diaphragms, showerheads, faucet aerators, pre-rinse nozzles, and clothes washers.

 

Project Title:  Sonoma Valley County Sanitation District Tertiary Treatment Plant Upgrade
Date Started:
October 23, 2006
Date Completed:
   June 30, 2008
Description:
    Work consisted of, but was not limited to, the construction of a 26 million gallon per day tertiary filter system, approximately 1,000 cubic yards of reinforced concrete, precast concrete structures, aluminum grating, aluminum stairs, aluminum railing, approximately 1,800 square feet of masonry block building, four vertical turbine pumps, miscellaneous pipe, chemical feed system (including meters, pumps and analyzers), tow 6,500 gallon polyethylene tanks, electrical system, and appurtenant work.

 

Project Title:  Wohler/Mirabel 12 kV Powerline Undergrounding and Overhead Powerline Modification Project
Date Started:
June 23, 2008
Date Completed:
  June 4, 2009
Description:
    The work consisted of construction of additions and modification to the Sonoma County Water Agency's Wohler/Mirabel electrical distribution syste, including, but without limitation, overhead pole line demolition, modifications and additions to the distribution system; improvements at Wohler Substation; and preparation for underground ductbanks at multiple sites.

 

Project Title:  Wohler Control Building Switchgear Replacement Project
Date Started:
April 15, 2008
Date Completed:
   March 4, 2009
Description:
    Work consisted of replacement of existing motor control center main air type 5kV circuit breaker current and potential transformers and protective relays with a compact vacuum type circuit breaker and solid state protective relay, including furnishing and installing the circuit breaker and relay, modifications to the switchgear to accommodate the new circuit breaker and transformers relay, coordination and arc flash studies with upstream protective devices, setting the relays arc flash study, start-up testing, and training Agency's personnel on the proper operation and maintenance of the equipment and systems

 

Project Title:  Water Transmission System Air Valve Upgrade, Phase 1 Project
Date Started:
September 8, 2008
Date Completed:
  April 1, 2009
Description:
    Work consisted of upgrading up to 43 of the Sonoma County Water Agency's combination air/vacuum relief valve (ARV) stations to comply with current California Department of Public Health guidelines, including but not limited to, modification of ARV vent piping such that it was vented above grade.  At each station, existing air valves(s) were replaced with new ARVs with a minimum diameter of two inches.  Work at each ARV station included, in some cases, excavation down to the aqueduct providing riser piping, vent piping, concrete vault with aluminum cover, ball valve, corp stops, and hot tapping the water transmission system piping and manways with working pressures up to 250 psi.